How to pour a concrete patio
Lay out a backyard patio, prepare the gravel base, and pour, finish, and cure the concrete slab.
This guide covers a simple patio slab on the ground, not a foundation. Use the calculators to estimate gravel, concrete, and rebar. Have your tools and helpers ready before the concrete arrives.
Calculators for this job
Tools
- Tape measure, stakes, string, and level
- Shovel, rake, and plate compactor
- Drill, wheelbarrow, and concrete rake
- Straight screed board and bull float
- Edger, groover, and concrete broom
Materials
- Form boards, stakes, and screws
- Compactable gravel base
- Rebar, tie wire, and rebar chairs
- Ready-mix concrete or bags for a very small pad
- Clean burlap and plastic sheeting for curing
Steps
Check the rules and call 811
Ask your local building department about permits, setbacks, and drainage rules, and check any HOA requirements. Call 811 before digging or driving stakes and wait for utilities to be marked. Ask about private lines that may need a separate locator.
Lay out and square the patio
Mark the slab edges with stakes and string. Measure the sides, then measure across both diagonals. Adjust the strings until the side lengths are right and the diagonals match.
Remove sod and soil
Dig down from the planned finished surface to make room for the slab and base. A typical patio uses 4 inches of concrete over 4 inches of compacted gravel. Remove roots and soft soil, and firm up the ground before adding gravel.
Build and slope the forms
Stake and brace the form boards so they cannot bow during the pour. Set their top edges at the finished slab height, with a slope of about 1/8 inch per foot away from the house unless local rules or site conditions call for more. Recheck the diagonals and keep the slab clear of siding and weep holes.
Spread and compact the gravel
Spread gravel in thin layers and compact each layer with a plate compactor. Check the depth from the top of the forms to the gravel at several points. Leave room for the full slab thickness across the patio.
Set the rebar on chairs
Lay out and tie the rebar grid as required for your slab. Set it on chairs so the steel sits near the middle of the slab instead of lying on the gravel. Keep the bars back from the forms as required and check that the chairs stay in place during the pour.
Order the concrete
Use the concrete calculator with the inside form dimensions and slab thickness. Add a little extra for uneven spots and spillage, and confirm the order with your supplier. Use ready-mix for a full patio and consider bags only for a very small pad.
Pour, screed, and float
Start at the far end and spread concrete evenly without moving the rebar. Draw a straight screed board across the form tops with a sawing motion, adding concrete to low spots as you go. Run a bull float over the surface before bleed water appears, then wait for any surface water to disappear before finishing.
Cut control joints and broom the surface
Use a groover to cut control joints about every 8 to 10 feet, making panels as square as possible. For a 4-inch slab, cut the joints at least 1 inch deep. Pull a concrete broom across the surface while it is still workable to leave a slip-resistant finish.
Keep the slab damp as it cures
Once the surface is firm enough not to mark, cover it with damp burlap and plastic and keep the burlap damp. Follow the supplier's curing instructions and protect the slab from drying out. Plan to wait about a week before light use, or longer if the supplier recommends it.
Tips
- Pour on a mild day. Avoid hot sun and rain, which can make the concrete harder to finish.
- Have at least two helpers ready before the truck arrives. Assign someone to spread the concrete while others screed and finish.
- Check whether the truck chute can reach the forms. If it cannot, arrange to rent a concrete wheelbarrow or book a pump before pour day.
Safety
- Wet concrete can burn skin. Wear waterproof gloves, long sleeves, eye protection, and rubber boots. Wash off splashes right away with clean water and remove any clothing soaked with concrete.
- Get help lifting concrete bags and use a cart or wheelbarrow to move them.
- Always call 811 before digging and wait for the required utility marks before you start.