Prepare and grade the soil, lay sod in staggered rows, then water it while the roots take hold.
This guide covers laying sod on prepared soil. Allow time before installation for utility marking and soil test results. Plan to lay all the sod on the day it arrives.
Calculators for this job
Tools
- Tape measure and straightedge
- Sod cutter or flat shovel
- Tiller and landscape rake
- Lawn roller and cart
- Sharp sod knife, hose, and sprinkler
Materials
- Sod suited to your yard
- Topsoil or finished compost as needed
- Soil amendments recommended by your soil test
Steps
Choose the grass and measure the lawn
Note how many hours of direct sun the yard gets and ask a local supplier which grasses suit your region. In much of the South, Bermuda does best in full sun, while some St. Augustine varieties handle partial shade. Measure the lawn in feet and check how many square feet the supplier puts on each pallet.
Mark utilities and test the soil
Contact 811 before tilling or digging and wait for the utilities to be marked. Locate private sprinkler lines and other private lines separately. Send a soil sample for testing and wait for recommendations before adding fertilizer or lime.
Remove grass and weeds
Strip old turf and weeds with a sod cutter or flat shovel. If you kill them with a lawn herbicide instead, follow the label, including how long to wait before laying sod. Rake out roots, rocks, and debris.
Loosen and grade the soil
Till the soil where it is safe to do so. Add topsoil where needed to build up low spots, or mix in finished compost if your soil needs it. Rake a smooth grade that slopes away from the house. Along walks, leave room for the sod's thickness so the finished lawn sits even with the paving.
Firm and dampen the base
Make a light pass with a lawn roller to settle the soil, then rake out bumps and fill any dips. Lightly water the surface so it is damp, not muddy. Arrange delivery for a day when the base is ready and you can lay all the sod before it dries out.
Lay the first row and stagger the seams
Lay the first row along a straight walk, driveway, or string line. Butt the edges together without overlapping or stretching the pieces. Start the next row with a half piece so the end seams are staggered like brick.
Trim around beds and walks
Use a sharp sod knife to cut around planting beds and paving. Fit each cut piece snugly against the next one, and avoid leaving narrow strips at the edges where they can dry out.
Roll and water right away
Pass a light lawn roller over the sod to press the roots against the soil. Water deeply right away, lifting a corner to check that the soil underneath is moist. On a hot day, water finished sections as you go instead of waiting for the whole lawn.
Keep the sod moist while it roots
Water daily for the first two weeks as needed to keep the sod and soil underneath moist, not soggy. Adjust for rain, heat, wind, and local watering rules. Once the sod resists a gentle tug, gradually water less often and more deeply.
Tips
- Start along the longest straight edge and never stretch the pieces to close a gap.
- Stay off the new lawn for about two weeks and longer if it has not rooted.
- Mow for the first time only when the sod resists a gentle tug and the ground is firm enough for the mower.
Safety
- Sod rolls and pallets are heavy. Lift rolls with your legs, move them with a cart, and have the supplier unload the pallets.
- Wear gloves when handling sod and cut away from your body with the sod knife.
- Contact 811 before tilling or digging and follow the instructions for working near marked lines.