Hang drywall on a ceiling and walls, then tape, smooth, prime, and paint it.

About 4 to 6 days, mostly waiting for mud to dry Moderate

This guide covers drywall in one room with exposed framing. Use the calculators to estimate sheets, mud, tape, and paint. Allow time between coats for the mud to dry.

Start this project

Calculators for this job

Tools

  • Tape measure, pencil, and drywall T-square
  • Utility knife and drywall saw
  • Drywall lift and screw gun or drill with a depth-setting bit
  • Taping knives and mud pan
  • Sanding sponge, paint roller, and brush

Materials

  • Drywall sheets
  • Drywall screws sized for the board and framing
  • Paper joint tape and joint compound
  • Outside corner bead
  • Drywall primer and wall paint

Steps

  1. Check the framing and rough-in work

    Check that studs and ceiling framing are straight, dry, and secure. Add backing where sheet edges need support. Make sure insulation is in place and electrical and plumbing work is finished and inspected if required before you cover it.

  2. Mark the framing

    Mark the center of each wall stud on the floor and at the top of the wall. Mark ceiling joist locations at the tops of the walls so you can find them after lifting a sheet. Transfer the upper stud marks to the finished ceiling before hanging the walls.

  3. Hang the ceiling first

    Use a drywall lift or work with a helper so you do not have to hold a sheet overhead alone. Run the long edges across the joists unless your ceiling system specifies otherwise. Keep sheet ends on framing and stagger the end joints in neighboring rows.

  4. Hang the wall sheets horizontally

    Start with the top row, snug against the ceiling, then hang the lower row. Stagger the end joints between rows and land them on studs. Keep sheet joints away from door and window corners, and leave a small gap at the floor.

  5. Cut openings for outlets and switches

    Turn off the breaker and verify the power is off before working around electrical boxes. Measure each opening from the sheet edges and mark it on the face. Cut it with a drywall saw before fastening that sheet, and check that it fits without covering the box.

  6. Set the screws as you hang each sheet

    Use the spacing required for your board, framing, and local code. A common screw schedule is no more than 12 inches apart on ceilings and 16 inches on walls, but some assemblies need closer spacing. Set the heads just below the surface without tearing the paper. If a screw tears through, set another one nearby in sound paper.

  7. Set corner bead and tape the joints

    Install outside corner bead straight and secure using the method the bead maker specifies. Spread the first coat of mud on flat seams and press paper tape into it. Fold paper tape down the center for inside corners and bed both sides in mud. Smooth out bubbles without squeezing all the mud out from under the tape.

  8. Build up three coats of mud

    Count the tape coat as the first coat. Cover screw dimples and corner bead as you coat the joints. Let each coat dry fully, scrape off ridges, then spread the second and third coats wider than the one before. Feather the edges into the board so the joints do not show.

  9. Sand, prime, and paint

    Once the last coat is dry, sand lightly without scuffing the drywall paper or exposing the tape. Remove the dust, fix any flaws, and let the repairs dry before sanding them smooth. Apply drywall primer and let it dry, then paint according to the label.

Tips

  • Use 1/2-inch board for typical walls and moisture-resistant board on bathroom walls outside wet areas. Use ceiling-rated board or 5/8-inch board where required by the span, local code, or assembly.
  • Buy a few extra sheets for cutting mistakes, especially if the room has lots of openings.
  • Hold a light at a low angle along the wall to spot ridges and dips before priming.

Safety

  • Wear eye protection and a properly fitted particulate respirator, such as an N95, when sanding drywall compound.
  • Use a drywall lift or a helper for ceiling sheets. Do not try to hold a full sheet overhead by yourself.
  • Turn off the breaker before cutting around any electrical box that could be live, and verify the power is off before cutting.

Estimates only. Check quantities with your supplier before you buy. © 2026 HouseCalcs