How to add attic insulation
Check the insulation you have, seal air leaks, and add batts or loose-fill to reach the right depth.
This guide covers adding insulation to the floor of a vented attic, not to the underside of the roof. Fix any roof leaks before you start. If you see gray-brown, pebble-like insulation, stop before touching it or pushing a ruler into it. It may be vermiculite that contains asbestos.
Calculators for this job
Tools
- Tape measure, ruler, and marker
- Stable ladder and work light
- Sturdy walk boards
- Caulk gun, utility knife, and straightedge
- Rental insulation blower for loose-fill
Materials
- Unfaced insulation batts or loose-fill insulation
- Compatible caulk or foam for ordinary air leaks
- Soffit baffles and insulation dams
- Hatch weatherstripping and compatible insulation
- Marked depth stakes for loose-fill
Steps
Set up a safe place to walk
Light the attic and lay a sturdy walk board across several sound ceiling joists. Secure it so it cannot shift or tip. Step only on joists or supported boards, never on the ceiling between them.
Measure what is already there
Measure the depth in inches at several spots without packing the insulation down. Note the type if you can identify it safely. Look up your climate zone in ENERGY STAR's Recommended Home Insulation R-Values table and use the chart and product labels to plan how much R-value to add. Use the insulation calculator to estimate quantities.
Check clearance around heat sources
Identify chimneys, flues, and recessed lights before covering anything. Follow the equipment labels and local code for the required clearances. Use suitable noncombustible barriers to keep insulation back where needed, and never cover recessed fixtures that are not rated for insulation contact (IC). If you cannot verify the rating or clearance, have a pro check it before proceeding.
Seal air leaks first
Seal gaps at the tops of walls and around pipe and wire openings with compatible caulk or foam where allowed. Turn off power before working around light fixtures. Seal gaps at recessed lights only with a method approved for the fixture, and never use ordinary foam around hot flues, chimneys, or lights.
Install baffles at the soffits
Fit baffles between the rafters at the soffit vents so air can flow from the eaves into the attic above the insulation. Use insulation dams where needed to keep loose material from sliding into the vents. Keep the inlet and outlet vents open.
Add batts or blow in loose-fill
Roll unfaced batts across the joists, perpendicular to the existing layer between them. Butt the edges together without compressing the batts, and do not add a new vapor barrier on top. For loose-fill, rent a blower, have a helper feed it, and follow the product's coverage chart for bag count and installed depth.
Insulate and weatherstrip the hatch
Apply weatherstripping where the hatch meets its frame and attach suitable insulation to the attic side without blocking the hatch from closing. If using loose-fill, add a dam around the opening so insulation does not spill when you open it.
Check the finished depth
Use marked rulers or depth stakes to check several spots, including near the eaves without blocking the baffles. Compare loose-fill depth with the product's coverage chart and fill low spots. With batts, check for gaps and places where the material was squeezed flat.
Tips
- Work in the cool early morning, before the attic heats up.
- Bring a work light so you can see the joists, wires, and low spots.
- Mark the target depth on a ruler stake every few feet before blowing in loose-fill so you can keep the layer even.
Safety
- Step only on joists or supported boards, never between them. Watch for nail points sticking through the roof deck.
- Wear a properly fitted particulate respirator, goggles, long sleeves, and gloves. Keep the attic ventilated and take breaks outside the attic if it gets hot.
- If you see gray-brown, pebble-like vermiculite, stop and leave it undisturbed. Have an asbestos professional assess it and arrange testing if appropriate before continuing.